The City of Encinitas approved the coastal development permit for the Paul Ecke Elementary School rebuild on Oct. 28, clearing the project's biggest remaining regulatory hurdle.

The permit covers reconstruction of the campus at 185 Union Street in Old Encinitas. The project, funded by voter-approved Bond Measure Z, carries a $60 million price tag, according to the San Diego Union-Tribune.

The new campus will include an administration building, 10 classroom buildings, a library, a kitchen, a lunch shelter and a multi-purpose building, according to the city's notice of decision. The permit also covers underground utilities, stormwater facilities, parking lots, athletic fields, landscaping and a temporary construction trailer.

Development Services Director Scott Drapkin signed the approval. Senior Planner Christina M. Bustamante served as the project planner.

The approval followed an administrative hearing on Oct. 27 at City Council Chambers. No public comments were received at the hearing, according to the notice of decision.

The permit ends months of conflict between the city and the Encinitas Union School District over the project. Sticking points included stormwater drainage, traffic queuing on Vulcan Avenue during school drop-off and pick-up, right-of-way dedications and roadway frontage improvements.

The two sides announced in mid-October that they had resolved "all outstanding issues," according to the Union-Tribune. City Manager Jennifer Campbell said at the time that city employees and district representatives had been meeting almost daily for several weeks.

The dispute had drawn parents to the Sept. 23 City Council meeting. In coverage published in September, the Union-Tribune reported that parent Mary Anne Mendenhall said, "If we go to litigation, everybody loses."

Students have been displaced during the rebuild. Kindergarten through third-grade students are attending El Camino Creek Elementary, and fourth through sixth graders are at Park Dale Lane Elementary, according to the Union-Tribune.

The district had previously said it no longer expected the school to reopen in time for the 2027-28 school year because of permitting delays. Whether the Oct. 28 approval changes that timeline is not stated in the permit documents.

The approval includes conditions requiring the district to monitor vehicle queuing and traffic circulation on North Vulcan Avenue, Union Street and Hermes Avenue once the school reopens. If the city determines that vehicle lines on public roads create safety problems, the district must develop and pay for corrective measures.

Two grading permits for the project remain under review, according to the notice of decision. Building construction permits could be issued as soon as late November, Campbell said in mid-October.

A 1929 schoolhouse on the property will be preserved and renovated, though the notice states it will no longer qualify as a historic resource after the work. A second historic building, known as Building A and built in 1947, was documented before demolition.

The approval can be appealed to the Encinitas City Council within 10 calendar days. Because the school sits in the coastal zone, the California Coastal Commission can also hear appeals after it receives the city's notice of final action.